Renovation progress on Rinpoche's Stupa and Gompa

Benefiting nice weather conditions, the work is going on at a swift pace.
The Chorten scrapping is completed and we are now curing with water before to start plastering.
Plastering would need approximately 7 days and painting another 10 days.
Adding tiles on the steps would take another 3 days.
So we expect work on the Stupa to be completed by the third week of November.





For the Gompa, the work is well on its way. The scrapping is already completed and the plastering needs another 3 to 4 days. Where it was possible the painting has already been started. All together we need another 3 weeks before completion.







Your support is greatly appreciated.